Well this is how i think it happens. In the next column
will be how it actually happens and if I get clever I'll lay out the web
page a bit better. |
| PLAN |
|
ACTUAL
|
| 1) the garage comes down |
|
1) Friday, July 18, took ONE day |
| 2) the site gets surveyed |
2) |
| 3)dig hole |
|
3) Saturday, August 2, 2003 |
| 4)throw the slab and basement |
|
4)Wednesday, August 6 - 16 no slab, just footings and
basement walls |
| 5)start framing, windows, doors |
|
5) started 18 August, sills, beams,
ground floor deck +
walls |
| 6)roofing, trim, porches,decks |
|
6) first floor decking + walls
6 September |
| 7)shingles |
|
7) framer finished Oct 30,
2003 (took 11 weeks) |
| 8)interior, bathrooms, kitchen |
|
8) Both new + old house roof
shingled Nov 3, 2003 (5 days) |
| 9)floors, plastering, tiling, finish carpentry |
|
9) Side wall shingling started thurs Nov 20-21
+25th finished |
|
|
10) trim on windows |
|
|
The BIG FREEZE is here so all work has to halt! January
17, 2004 |
|
|
11) Garage floor concrete completed April 16, 2004 |
|
|
12) Wait for garage doors to be delivered PLUS cedar
tongue and groove |
|
|
13) The perimeter is secure!! Garage doors are
installed May 1, 2004 |
|
PUNCH LIST |
|
14) Electric motors installed "Overhead
Door" |
|
|
14) Driveway needs to be graded.......thank you
Richard! June24, 2004 |
|
|
|
|
|
.. |